M/A | Milestones (M) and activities (A) | Estimated Start Date | Estimated Completion Date | Target Date | Completion Date | Responsible Parties | |
---|---|---|---|---|---|---|---|
0 | Complete Project Proposal | May 1, 2021 | May 27, 2021 | May 27, 2021 | Hans B. | ||
5 | Complete Project Scope Statement | June 7, 2021 | October 11, 2021 | Hans B. | |||
6 | Phase 0 | Stormin | Formin | Normin | May 2021 | Aug 2021 | October 2021 | Team | |
10 | Phase 0 | Establish the mapping templates for C-CDA R2.1 and Companion Guide R2 (templates associated with USCDI) to US Core where possible, otherwise FHIR R4 (v4.0.n) Will comply with the C-CDA on FHIR IG. (v1.1.n), but may evolve/revise this work if this project reveals issues. | May 17, 2021 | October 25, 2021 | Natalie/Jay/Ken | ||
15 | Phase 0 | Establish the mapping templates for FHIR R4 (v4.0.n) Resources to C-CDA, used in the other map. | June 1, 2021 | October 25, 2021 | Natalie/Jay/Ken | ||
20 | Phase 0 | Establish the list and priority order for mapping the C-CDA R2.1 and Companion Guide R2 templates to FHIR R4 (v4.0.n) | June 7, 2021 | October 25, 2021 | Lisa/Natalie | ||
25 | Phase 0 | Establish the list and priority order for mapping the FHIR R4 (v4.0.n) US Core profiles to C-CDA R2.1 and Companion Guide R2 templates. | June 21, 2021 | October 25, 2021 | Lisa/Natalie | ||
Phase 1 | Allergy Concerns | August 2021 | October 25, 2021 | Team |
4 Comments
Lisa R. Nelson
When the project gets started, we need to determine what format the SMEs will need to review and express the mappings. We also need to agree on the content that will be included in the Web IG that will ultimately be published as the artifact to hold and organize all this work. This will be similar to the Web IG produced for HL7 Version 2 to FHIR mappings.
We also need to consider how the SMEs will work so that we can divide an conquer the body of work. We should also consider how vendors engaged in the project would "test" the use of the mappings to inform their implementations. The output/experience of the implementations of the mappings were very telling in terms of vetting the accuracy of the maps. (Google, Lantana, MaxMD, MDIX, DHIT etc.)
We should draft a schedule for Balloting the IG. We also should use the C-CDA IATs to promote and gain more implementer support (July 28th, October 21st)
We will use zulip to hold discussions about this project: https://chat.fhir.org/#narrow/stream/179191-cda-to.20fhir
Lisa R. Nelson
We need to work with HL7 to determine how we will produce the Web IG.
We need to work with HL7 to establish how one CDA IG references the mapping guidance produced in this CDA IG.
Lisa R. Nelson
We take a page from the Collaborative Template Review Pilot to establish a way of working that commits to having resources from this project reach-out to go and meet with the WG responsible for the corresponding FHIR Resources to gain consensus and collect input/feedback from all involved.
Lisa R. Nelson
Should we use the entry templates to organize the mapping work (plus US Realm Header template).